2020
RWE begins approaching landowners
The earliest records show RWE engaging landowners in leases and nearby property owners in “good neighbor” agreements.
November 2023
PA 233 enacted
Michigan lawmakers pass Public Act 233, giving developers of large-scale wind, solar and energy storage facilities the option to seek state approval instead of local approval.
November 2024
PA 233 takes effect
The law takes effect, moving final siting decisions for qualifying facilities to the Michigan Public Service Commission when developers choose that route.
August 2025
RWE presents Silver Maple Solar to the township
After spending nearly five years securing land, RWE presents its plans for Silver Maple Solar to Zeeland Charter Township.
April 2026
RWE files with the MPSC
RWE bypasses local zoning and files its application for Silver Maple Solar with the state under PA 233.
April 2026
Township Board opposes the development
The Zeeland Township Board unanimously opposes Silver Maple Solar.
April–September 2026
Township takes legal action
The township intervenes in the MPSC case, files a lawsuit challenging PA 233 and adopts a moratorium on new data centers and energy facilities.
May 2026
Court of Appeals ruling
In a statewide PA 233 case, the Michigan Court of Appeals rules that counties must be included as affected local governments. RWE later pauses its application to respond.
August 2026
MPSC approves first PA 233 siting certificate
The MPSC approves its first PA 233 facility, a 90-megawatt solar facility in Ingham County, through a settlement agreement with three host townships.
September 2026
RWE refiles with the MPSC
RWE refiles its Silver Maple Solar application with the MPSC under Case No. U-22071.
September 2026
Township launches “Your Township. Your Voice.”
The township launches its initiative to listen to residents, respond to their concerns and share information about Silver Maple Solar.
Nov. 19, 2026 · Upcoming
Community Update
Join us at the Zeeland Charter Township Offices, 7–8:00 p.m.